KIA Sportazh - Kia Sportage
Controls and operation receptions
Current leaving and service
The engine
Systems of cooling, heating, ventilation and air conditioning
Power supply systems, managements of the engine/decrease of toxicity of the fulfilled gases and release of the fulfilled gases
   Security measures and the general rules accepted at service of components of fuel paths of internal combustion engines
   The power supply system of petrol engines
   The power supply system of diesel engines
      The general information
      Power supply system checks
      Adjustment of turns of idling
      Adjustment of installation of phases timing (the injection moments)
      Removal and installation турбокомпрессора
      Removal and installation of a pedal of gas, adjustment of a cable of gas
      Removal and installation of a fuel tank
      Removal and installation of the gauge of a stock of fuel
      Removal and installation of a jellied mouth of a fuel tank
      Removal and installation of the fuel filter
      Removal and installation ТНВД
      Removal and installation of atomizers
   Control systems of the engine and decrease in toxicity of the fulfilled gases
   System of release of the fulfilled gases
Systems of an electric equipment of the engine
Five-step manual box of a gear change
Automatic transmission
Transmissionnaja line
Brake system
Suspension bracket and steering
Body
Onboard electric equipment
Control кузовные the sizes
Schemes of electric connections




Kia Sportage>> Power supply systems, managements of the engine/decrease of toxicity of the fulfilled gases and release of the fulfilled gases>> The power supply system of diesel engines>> Removal and installation of atomizers

Removal and installation of atomizers

Details of installation of a fuel atomizer

1 — the Lock nut of a returnable line
3 — the Returnable tube
4 — the Washer

5 — the Atomizer
6 — the Sealing element
7 — the Corrugated sealing washer


 PERFORMANCE ORDER

    Disconnect from an atomizer a line of giving of fuel. Give a lock nut and disconnect a returnable line. Remove a washer. Turn out and take an atomizer. Remove a sealing element and a corrugated sealing washer. Disassemble an atomizer on making components.
1 — the atomizer Case
2 — the Case of the needle valve
3 — the Remote plug
4 — Press a finger
5 — the Press spring
6 — the Adjusting washer
7 — the Holder
8 — the Washer
9 — the Nut
    Check up all components on presence of mechanical damages, make sure of density of pressing of the needle valve to the saddle.
    Develop the case of the needle valve vertically, fill a needle approximately for 2/3 lengths the case and release, - it should fall on a saddle under a body weight.
    Collect an atomizer, having tightened the valve case in the holder with effort 78.4 98.1 Nanometers.
    Check up pressure of opening of a nozzle (the Section of Check of the power supply system see). Installation is made upside-down, - do not forget to replace all sealing elements, tighten an atomizer with demanded effort (58.8 68.6 Nanometers).