KIA Sportazh - Kia Sportage
Controls and operation receptions
Current leaving and service
The engine
Systems of cooling, heating, ventilation and air conditioning
Power supply systems, managements of the engine/decrease of toxicity of the fulfilled gases and release of the fulfilled gases
Systems of an electric equipment of the engine
Five-step manual box of a gear change
Automatic transmission
Transmissionnaja line
   The general information
   Coupling
   Distributing box
   Kardannye shaft
      The general data
      Check of a condition without removal from the car
      Removal, service and installation карданных shaft
   Bridges
Brake system
Suspension bracket and steering
Body
Onboard electric equipment
Control кузовные the sizes
Schemes of electric connections




Kia Sportage>> Transmissionnaja line>> Kardannye shaft>> Removal, service and installation карданных shaft

Removal, service and installation карданных shaft

Removal

Forward shaft

 PERFORMANCE ORDER

    Mark adjusting position of a shaft concerning a connecting flange of a leading gear wheel of the main transfer of the forward bridge, release fixing bolts/nuts, release the forward end of a shaft and tie it to chassis/suspension bracket elements.
    Mark adjusting position of a shaft concerning a connecting flange of a target shaft of a distributing box, release four fixing nuts, separate a shaft and take it from under the car.

Back shaft

 PERFORMANCE ORDER

    Mark adjusting position of a shaft concerning a connecting flange of a target shaft of a distributing box, release four fixing bolts/nuts, separate the forward end of a shaft from a distributing box and tie up it to chassis elements.
    Mark adjusting position of a shaft concerning a connecting flange of a leading gear wheel of the main transfer of the back bridge, release four fixing bolts/nuts, separate a shaft and take it from under the car.

Both shaft

 PERFORMANCE ORDER

    If there is a necessity for division jointed шлицами shaft sections, it is necessary to mark their adjusting position preliminary in order to avoid balancing infringement.

Service

 PERFORMANCE ORDER

    Carefully wipe components of assemblages карданных hinges. Clamp a shaft body in a vice with soft sponges.
    Mark position of components карданного the hinge from each other, - the wrong joint of components can lead to infringement of balancing of assemblage.
    Hooking a screw-driver with a flat sting, remove fixing шарнирную assemblage lock rings.
    Easily tapping on a collar with a hammer with soft brisk, take bearings крестовины. Remove a collar.
    By means of approaching выколотки beat out bearings and remove крестовину.
    Estimate a condition of components, in case of need prepare replaceable knots.
    Before assemblage fill in covers and rollers of bearings, and also in lubricant apertures крестовины greasing on литиевой to a basis (NGLI № 2).
    Fill крестовину in a shaft plug, - track correctness of combination of the landing labels put in the course of dismantle, - and by means of a hammer with soft brisk begin to knock two bearings.
    Plant on крестовину a collar карданного the hinge, - track correctness of combination of the landing labels put in the course of dismantle, - and by means of a hammer with soft brisk begin to knock two bearings.
    Fix assemblage by NEW lock rings, having tracked correctness of their landing in reception flutes.

Lock rings should be selected so that the starting effort проворачивания the hinge did not fall outside the limits an admissible range (sm of the Specification of Head Transmissionnaja a line). All four rings should be one thickness.


    Check up starting effort проворачивания шарнирной assemblages. Compare results of measurement to requirements of Specifications of Head Transmissionnaja a line, in case of need make corresponding updating by selection of lock rings of other thickness (see the table).

№ details

Thickness, mm

№ details

Thickness, mm

1757 25 171 1.22 1757 25 176 1.32
1757 25 172 1.24 1757 25 177 1.34
1757 25 173 1.26 1757 25 178 1.36
1757 25 174 1.28 1757 25 179 1.38
1757 25 175 1.30

    Connect shaft sections, - track correctness of combination of landing labels, then lay a shaft in prisms and by means of a measuring instrument плунжерного type define size of its bend. If the result of measurement exceeds limiting admissible value (Specifications of Head Transmissionnaja a line see), will measure a shaft.

Installation

 PERFORMANCE ORDER

    Installation is made in an order, the return to an order of dismantle of components, - track correctness of combination of landing labels and behind observance of requirements of Specifications of Head Transmissionnaja a line to efforts of a tightening of carving connections.